June 4, 2025

Depot Street Project

Dear Resident/Business Owner:

Town of Douglas is upgrading the water system on Depot Street. In order to complete the upgrade, contractor C. Naughton will be installing a temporary bypass water system on Depot Street, starting on June 9th.

On June 16th C. Naughton will begin converting residents to the temporary bypass water system and may need access inside residences to connect the water.

The entire water system upgrade project will continue to approximately August 4th, with normal working hours being from 7AM to 3:30/5:00PM.

Traffic patterns may/will change during this portion of the work. During pipe installation, sections of the roadway will be closed to thru traffic. Residents will have access to their homes at all times during construction, using a different direction.

Please be aware of all police details and directional signage. Caution and extreme vigilance through work zone areas is advised during all hours.

We appreciate your patience and apologize for any inconvenience that this may cause.

Facebook Twitter Email

Latest Update:

December 30, 2025 9:58 AM

DEPOT ST WATER MAIN PROJECT & TRAFFIC UPDATE – 12/30/2025
 
Work to rebuild a collapsed retaining wall at 59 Depot Street is now complete. The collapsed portion of the 14 foot high, large stone retaining wall has been rebuilt, along with installing a new catch basin and a new metal guardrail. The temporary Jersey barriers and portable traffic lights have been removed.
 
There is no work scheduled for the rest of the winter season.
 
Remaining work that will start in the spring, weather dependent, is as follows:
 
  • The entire length of Depot Street will be reclaimed (grind the existing pavement to a depth of 12 inches);
  • Regrade the fresh reclaimed surface, removing excess material;
  • Install the binder paving base;
  • Replace existing sidewalks with new granite curb and concrete sidewalk;
  • Raise road structures in preparation for finish paving layer (manhole covers, gate boxes, etc.);
  • Restore all disturbed areas (lawns, driveways, sides of roadway, etc.);
  • Pave the finish layer of asphalt;
  • Paint pavement markings (double yellow centerline, crosswalks, stop bars, etc.).

Prior Updates

View All Updates
December 1, 2025 12:14 PM

DEPOT STREET WATER MAIN PROJECT & TRAFFIC UPDATE – 12/01/2025
Work to rebuild a collapsed retaining wall located at 59 Depot Street will start on Monday, December 1st, and last approximately three weeks.
Jersey barriers will be positioned on the double yellow center line, where the southbound lane to Railroad Ave will be closed to all thru traffic, leaving the northbound lane to Main Street open to alternating one-way traffic.
Portable traffic lights will be positioned on each end of the Jersey barriers to control traffic.
Speed limit within the alternating one-way traffic zone will be 20 MPH.
Please use extreme caution and vigilance at all times when driving through all work zone areas.

September 16, 2025 1:55 PM

DEPOT ST WATER MAIN PROJECT & TRAFFIC UPDATE – 9/16/2025
Water main work on Depot Street continues where there will be a half road closure with alternating one-way traffic pattern in the vicinity of 58-59 Depot Street on Wednesday (9/17) to install a catch basin concrete structure.
In addition, on Friday (9/19), paving crews will be paving only the one lane over the water main trench. Expect half road closure with alternating one-way traffic pattern in the vicinity of the paving operation.
Use extreme caution and vigilance at all times when driving through all work zone areas.